Ports Operation Programme: Ndayane, Sendou, Ziguinchor, Foundiougne–Dakhonga
New
Transport
Port Construction and Development Program
Axis 3: Sustainable Spatial Planning and Development
SO.3.5. Develop connectivity infrastructure
Funding (public et prive) :
735,000,000,000 FCFA
Project leader

Ministry of Fisheries, Maritime Infrastructure and Ports

Autonomous Port of Dakar
Project description
Faced with changing market requirements and new technologies, Senegal must adapt its port infrastructures to support growth and meet logistic challenges. This includes rehabilitating regional ports and constructing deep-water ports such as Ndayane and Bargny.
Intervention zones
🇸🇳 5 région(s) d'intervention
⏳ Chargement de la carte...
Funding (public et prive)
735,000,000,000 FCFA
Overall Objective:
- Improve the competitiveness of Senegal’s ports.
Specific Objectives:
- Increase the hosting capacity of port facilities
- Promote the development of production, processing and storage industries
- Strengthen the hub-port role
- Develop port hubs
- Support growth poles through port connections
Expected results
- Port ecosystem linked to economic hubs
- Efficiency of port operations improved
- Competitiveness improved
- Operational capacity increased
- Job-creating activities developed
- Trade balance improved
Key milestones
2026
- Upgrading of regional ports and start of activities in Bargny
- Commissioning of regional ports
2028
2029
- Completion of the Ndayane industrial zone and transfer of container activities to Ndayane