Air Cargo Terminal (FRET Terminal)
New
Infrastructure
Airport Infrastructure Construction Program
Axis 3: Sustainable Spatial Planning and Development
SO.3.5. Develop connectivity infrastructure
Funding (public) :
30,000,000,000 FCFA
Project leader

Ministry of Land and Air Transport
Project description
The project consists of the construction, equipment and operation of an air cargo terminal with a handling capacity of 80,000 tonnes/year by 2035, offering high-quality services and optimal connectivity for goods. The project includes four main components:
- Development of the terminal platform, aircraft parking, taxiway and utility networks
- Construction of the hangar andadministrative buildings
- Equipment (cargo, security and fire protection)
- Operation
Intervention zones
🇸🇳 1 région(s) d'intervention
⏳ Chargement de la carte...
Funding (public)
30,000,000,000 FCFA
Overall Objective
- Increase the growth of the cargo volume handled at AIBD.
Specific Objectives
- Improve AIBD’s connectivity through new partnerships
- Promote technological innovation to improve cargo services efficiency
- Promote the development of import–export freight activities
- Enhance efficiency, productivity and quality of cargo operators at AIBD
- Modernise cargo handling and processing equipment
- Improve the quality of services offered to airlines and cargo operators
Expected results
- Significant growth in cargo volume handled at AIBD
- Strengthened connectivity with major international markets
- Increased attractiveness of AIBD as a logistics hub
- Increased number of air cargo operators
- Reduced processing time for import, export and transit goods
- Improved efficiency of cargo operations
- Increased satisfaction and loyalty of air cargo stakeholders
Key milestones
2025
- Partner search
- Start of works
2026
2027
- 2027 – Delivery of the FRET terminal
2028
2029